WSAZ - News - Headlines

NEW INFO: Additional Safety Measures Added Near I-64 Construction

By: WSAZ News Staff Email
Posted: Thu 5:41 PM, May 16, 2013

UPDATE 5/16/13 @ 5:30 p.m.
HUNTINGTON, W.Va. (WSAZ) -- Road work is causing some issues for drivers on I-64, but workers have tried to make things a little safer at the Hal Greer on ramp.

West Virginia Paving and the West Virginia Department of Highways have installed rumble strips and more "Stop Ahead" signs to warn drivers entering the interstate.

In addition, crews added "Merge Left" signs on the eastbound lanes before the on ramp to warn drivers that traffic is entering the interstate.

WV Paving and the WVDOH urge all drivers to obey the 50mph speed limit that is posted in the construction area.

The project is expected to be finished by September 28, 2014.



UPDATE 5/7/13 @ 6:05 p.m.
HUNTINGTON, W.Va. (WSAZ) -- Four miles of Interstate 64 has been squeezed to traffic, as the West Virginia Division of Highways continues its widening project through Cabell County.

"It's very tight through here," WVDOH Construction Engineer Chris Collins said. "There's not much room for error, so we're urging people to obey the speed limit."

The project will widen I-64 between Hal Greer Boulevard and Route 60.

"The biggest problem is speed," Collins said. "It's goes from 65 mph to 50 mph, and people need to pay close attention to the traffic signs."

One change, drivers will notice, is there will be more signs leading up on the entrance ramp on I-64 at Hal Greer Boulevard. It is a complete stop before merging into traffic. That sign is blocked from sight leading up the ramp.

"We do understand it's not best-case scenario for the situation," Collins said. "We are in the process of looking at some alternatives and making some changes in that area."



UPDATE 4/2/13 @ 1 p.m.
HUNTINGTON, W.Va. (WSAZ) -- Monday, April 8 is now the projected start date to begin construction on widening a portion of I-64 to six lanes in the Huntington area.

The construction project will take place between Exit 11, Hal Greer, and Exit 15, 29th Street.

The work was originally set to begin on March 11, but West Virginia Paving has been forced to delay the project every week, the past four weeks due to weather, according to the Division of Highways.

The latest start date was Thursday, April 4.

The project consists of adding an additional lane in both directions on the median side of the road, installing a median concrete barrier, and replacing the Cedar Crest Bridge with a new six-lane structure.

Jack Withrow with West Virginia Paving tells WSAZ.com that there will not be any more delays on the project.

Withrow says they will start Monday night with some milling up of the old pavement and paving the shoulders in preparation for installing barrier walls around the median.

The project is expected to be finished by September 28, 2014.

Keep clicking on WSAZ.com for the latest information.



UPDATE 3/25/13 @ 11:20 a.m.
HUNTINGTON, W.Va. (WSAZ) -- For the third week in a row, weather is delaying a project to widen a portion of I-64 to six lanes in the Huntington area.

The widening project will take place between Exit 11, Hal Greer, and Exit 15, 29th Street.

The work was originally set to begin on March 11, but the contractor has again put the project on hold until Monday, April 1 due to weather conditions, according to the Division of Highways

The project consists of adding an additional lane in both directions on the median side of the road, installing a median concrete barrier, and replacing the Cedar Crest Bridge with a new six-lane structure.

The project is expected to be finished by September 28, 2014.

Keep clicking on WSAZ.com for the latest information.



UPDATE 3/19/13 @ 9:30 a.m.
HUNTINGTON, W.Va. (WSAZ) – For the second week in a row, weather is delaying a project to widen a portion of I-64 to six lanes in the Huntington area.

The widening project will take place between Exit 11, Hal Greer, and Exit 15, 29th Street.

The work was originally set to begin on March 11, but on that day the contractor decided to delay the construction by a week due to impending bad weather.

Now the Division of Highways says the contractor is again delaying the widening work until Monday, March 25.

The project consists of adding an additional lane in both directions on the median side of the road, installing a median concrete barrier, and replacing the Cedar Crest Bridge with a new six-lane structure.

The speed limit in the area is being reduced to 50 MPH during construction.

The DOH says the contractor is required to maintain two-lane traffic in both the east and westbound lanes between 5 a.m. and 7 p.m. The contractor is permitted to have a lane closure in both directions between 7 p.m. to 5a.m.

The project is expected to be finished by September 28, 2014.

Keep clicking on WSAZ.com for the latest information.



UPDATE 3/11/13 @ 11:45 a.m.
HUNTINGTON, W.Va. (WSAZ) -- The start of work to widen a portion of I-64 to six lanes in the Huntington area is being delayed by one week.

The widening project will take place between Exit 11, Hal Greer, and Exit 15, 29th Street.

The work was set to begin Monday night, but due to impending bad weather this week, the Division of Highways says the widening work won’t start until Monday, March 18.

The project consists of adding an additional lane in both directions on the median side of the road, installing a median concrete barrier, and replacing the Cedar Crest Bridge with a new six-lane structure.

The speed limit in the area is being reduced to 50 MPH during construction.

The DOH says the contractor is required to maintain two-lane traffic in both the east and westbound lanes between 5 a.m. and 7 p.m. The contractor is permitted to have a lane closure in both directions between 7 p.m. to 5a.m.

The project is expected to be finished by September 28, 2014.

Keep clicking on WSAZ.com for the latest information.



ORIGINAL STORY 2/28/13
HUNTINGTON, W.Va. (WSAZ) -- After several years of delay, a project to widen I-64 to six lanes in the Huntington area is set to begin in a couple of weeks.

The Division of Highways announced Thursday that the widening project will take place between Exit 11, Hal Greer, and Exit 15, 29th Street.

The work will consist of adding an additional lane in both directions on the median side of the road, installing a median concrete barrier, and replacing the Cedar Crest Bridge with a new six-lane structure.

Work is scheduled to start on March 11, with prep work starting Monday. The speed limit in the area will be reduced to 50 MPH during construction.

The DOH says the contractor is required to maintain two-lane traffic in both the east and westbound lanes between 5 a.m. and 7 p.m.

The contractor is permitted to have a lane closure in both directions between 7 p.m. to 5a.m.

Signs are already going up to warn drivers about the construction project.

The project is expected to be finished by September 28, 2014.

Keep clicking on WSAZ.com for the latest information.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus
Click here to send us your pictures and video pix@wsaz.com

Call To Check Road Conditions

  • WEST VIRGINIA: (877) 982-7623
  • KENTUCKY: (866) 737-3767
  • OHIO:Click here

Click here for online road conditions

WSAZ.com Sponsor Sections & Links

Download the WSAZ First Warning Weather App to your iOS or Android devices. It's FREE, sponsored by St Mary's Medical Center.
SOMC-Very good things are happening here
Very good things are happening here. Click here to learn more
Click here for closing and delays
Click here for school closings and delays. Sponsored by Buckeye Hills Career Center.
West Virginia Lottery nightly @ 6:59pm on WSAZ click here for numbers and drawings
Check out the WV Lottery HD Weather Cameras here. Watch the Lottery Live Monday - Saturday @ 6:59pm on WSAZ NewsChannel 3.
Ohio Lottery
Watch the Ohio Lottery Drawings weeknights @ 7:29pm and Cash Explosion Saturday @ 7:30pm on WSAZ NewsChannel 3.
Making Moms LIfe Easier - with Diane Dimoff
Follow @MomsEveryday daily video tips from the experts about health, money, family fun, and more!
WSAZ Children's Charitable Foundation
Remember WSAZ Children's Charities as we end the year. Click here to donate. Thank you.
A WSAZ Salute to...
Join us as we salute our communities, fairs and festivals. Scheduled are Pikeville, KY, Mason Co, WV. Jackson Co, WV, Logan, WV, Putnam Co, WV, South Charleston, WV, Barboursville, WV, Milton, WV, Paintsville, KY, Gallipolis, OH
WSAZ NewsChannel 3 645 Fifth Avenue Huntington, WV 25701 304-697-4780 WSAZ Charleston 111 Columbia Avenue Charleston, WV 25302 304-344-3521
Gray Television, Inc. - Copyright © 2002-2013 - Designed by Gray Digital Media - Powered by Clickability
User Agent: CCBot/2.0 - 193836741